| Process Group | PMBOK | Knowledge Area Process | Why? (inputs) | How? (tools and techniques) | What? (outputs) |
| Planning | 11.1 | Risk Management Planning |
|
|
|
| Planning | 11.2 | Risk Identification |
|
|
|
| Planning | 11.3 | quaLitative Risk Analysis |
|
|
|
| Planning | 11.4 | quaNtitative Risk Analysis |
|
|
|
| Planning | 11.5 | Risk Response Planning |
|
|
|
| Controlling | 11.6 | Risk Monitoring and Control |
|
|
|
10. Retention = Assume
11. Deflect = Transfer
12. Risk¨s 3 factors = probability, impact, and the event itself.
13. BCR(benefit cost ration) = NPV of revenue divided by NPV of cost ´ if = to 1 or more, do the project.
14. Risk management = identify, analyze, and respond to risk factors and document.
15. Risk Event Status = probability of occurrence + severity of consequence.
16. Response planning = mitigation deflection, and contingency planning.
17. Method of reducing risk is to hold functional managers accountable for time/cost estimates. Hire and expert to product better estimates of the future costs. Perform statistical analysis to improve quality of forecasts.
18. A project manager¨s objective when sub-contracting is to shift as much of the risk possible to the sub while maintaining some degree of incentive for improving efficiency and economic performance.
19. When entering a contract whit a buyer, a project manager should try to shift as much of the risk tot he buyer as possible.
20. During what phase is the risk the highest? Conceptual
21. During what phase is the amount at stake the highest? Termination
22. Uncertainty = the complete absence of information.
23. Certainty = all information for making the right decision is available.
24. Know how to calculate a decision tree¨s cumulative probability.
25. PV = amount of payment in N years divided by (1 + interest)n
26. IRR = that rate of discount at which the sum of the positive present values is equal to the sum of the negative present values. OR cost equal revenue and project is a break even.